An old chapel stands in a field in front of cooling towers operating at the Dukovany nuclear power plant operated by CEZ AS, near the village of Dukovany, Czech Republic. Photo by MARTIN DIVISEK / EPA

April 22 (Asia Today) — The Czech Republic said its nuclear power project with South Korea is progressing on schedule, signaling potential expansion of cooperation that could extend to additional reactor construction and broader entry into the European market.

Petr Závodský, head of the Czech project company EDU II, said the Dukovany nuclear project has entered a key design phase just 10 months after the contract was signed with Korea Hydro & Nuclear Power.

“We received the first large-scale engineering package, including the conceptual design, last week,” Závodský said at a conference in Busan. “This marks a major contractual milestone, and site investigations have already been completed.”

He added that the next step is to submit licensing documents to Czech nuclear regulators within a year.

Tomas Ehler said the Czech government selected Korea Hydro & Nuclear Power based on its proven ability to complete projects on time and within budget.

“In nuclear projects, the most important factor is execution capability,” Ehler said. “The Korean proposal was evaluated as the best across all criteria.”

He emphasized that nuclear construction involves complex risks and requires close coordination between partners to identify and manage challenges early.

Officials also addressed concerns over a dispute involving France, saying the issue has effectively been resolved after being dismissed by Czech courts. They added that approval procedures with the European Commission for expanded reactor plans are ongoing and expected to be finalized by early 2027.

The Czech government reaffirmed its strategy to increase nuclear power’s share in its energy mix from about 30% currently to 50%-60% in the coming years.

A final decision on constructing additional reactors at the Temelin Nuclear Power Plant is expected next year, with progress on the Dukovany project serving as a key benchmark.

Ehler said that if both projects move forward with Korean participation, significant synergies could be achieved.

Závodský stressed that the partnership goes beyond a typical supplier relationship.

“The Czech Republic cannot build nuclear plants without Korean companies, and Korean firms cannot carry out the project without Czech partners,” he said. “This is a joint project, not just a client-supplier arrangement.”

Officials added that the cooperation could expand beyond the Czech Republic to other European countries, including Slovakia and Poland.

— Reported by Asia Today; translated by UPI

© Asia Today. Unauthorized reproduction or redistribution prohibited.

Original Korean report: https://www.asiatoday.co.kr/kn/view.php?key=20260422010007168

Source link

Leave a Reply

Discover more from Occasional Digest

Subscribe now to keep reading and get access to the full archive.

Continue reading