Bundaberg’s controversial Paradise Dam will need to be completely rebuilt after investigations found the wall has “too many issues” to be repaired.
Key points:
- Sunwater has recommended to build new Paradise Dam wall
- Detailed investigations revealed the existing dam wall couldn’t be repaired
- A business case for the new dam wall has commenced to determine cost to taxpayers
Experts investigating restoring the dam’s wall, which was lowered by 5.8 metres in 2020 due to safety concerns, have told the state government it cannot be mended or reinforced.
Instead, operator Sunwater has recommended the wall be wholly replaced immediately downstream of the current structure.
“The concrete quality of the dam means it cannot be repaired to last the many decades we expect from these assets,” Sunwater chief executive Glenn Stockton said.
“Sunwater understands the importance of public assets like this — they need to perform day-in, day-out.
“It’s become clear to us that Paradise Dam in its current form is not suitable to take forward.”
He said the work to lower the wall had reduced the risk of a failure, but the original plan to raise it again could not proceed.
“That was being done by raising the height of the existing structures and reinforcing those structures by buttressing with additional concrete around them,” he said.
“Our investigations have concluded that is not feasible.
“The structure that is currently there would not allow us to do that successfully and certainly wouldn’t allow us to do that over a period of time that gives us confidence into the future”
Return to capacity delayed
Early work on returning the wall to its original height began in 2023, with the state and federal government both committing to funding half of the $1.2 billion project.
Major work was due to start in 2024.
“We can’t continue to go down a path and look to work on an asset that’s compromised and not come out with an outcome that people have confidence in going forward,” Mr Stockton said.
“It’s a replacement structure in a sense that it returns the storage back to 300,000 megalitres.”
He said while some of the work from the restoration project would be used in the new build, it could take at least two years to work through new designs and environmental approvals.
“We appreciate that growers will be disappointed, we are disappointed,” he said.
“To be thinking that we need to do this sort of work on an asset that was relatively young in design terms is disappointing for us.
“But we needed to make a decision now to give ourselves and our customers and the community confidence in Paradise Dam of the future.”
Damned from the start
Built in 2005, the dam on the Burnett River about 100 kilometres south-west of Bundaberg, is the main water storage supplying the region’s agricultural industry.
It suffered significant damage during record flooding in 2013, and subsequent remedial works failed to address safety concerns.
In 2019, Sunwater announced the wall height would need to be reduced immediately to overcome structural issues, shocking irrigators who criticised the lack of consultation on the decision.
A subsequent Commission of Inquiry reporting to the state government found the original design, which was the first in Australia to use roller-compacted-concrete (RCC), was “incapable of meeting the required design values”.
No budget has been outlined for the rebuild project, but in a statement, Queensland Minister for Water Glenn Butcher said a business case had been started and new environmental approvals were being sought.
“The Queensland government will always listen to the experts and the expert advice tells us we cannot repair the existing dam wall,” he said.
“A new wall will ensure the dam is a lifelong asset and will deliver for an even longer term than promised by the repair.
“Reliable water supply is critical to jobs, growth and liveability in regional Queensland.”
He said early works at the site would continue “to ensure the new dam wall can proceed as quickly as possible, once all approvals have been obtained.”
He said the timeline and cost of the project would be confirmed once the business case and approvals were complete.
Paradise Dam timeline
- 1998 — Two days before a state election, opposition leader Peter Beattie promises to build a dam on the Burnett River within five years of being elected.
- 2002 — The Burnett River dam is approved for construction and immediately becomes controversial, with landholders claiming they were coerced into selling, and environmentalists lodging an appeal.
- 2003 — Now Premier, Peter Beattie turns the first sod on the $200 million project, named Paradise Dam after a former mining town.
- 2005 — Construction is completed and Sunwater becomes the operator of the dam.
- 2010 — Paradise Dam fills to capacity for the first time.
- 2010 — The dam wall experiences its first major flood event in December, when the Burnett River peaks at 7.9 metres.
- 2013 — The Burnett River experiences record flooding that is later revealed to have significantly damaged the dam wall.
- 2013 — Repairs cost more than $23 million, and despite being declared safe, there are ongoing concerns, prompting an independent investigation.
- 2013 — The independent report is released, resulting in $10 million worth of additional safety work.
- 2015 — Sunwater conducts several reviews, technical studies and improvement works.
- 2019 — On September 24, Sunwater announces the dam wall will be lowered immediately due to safety issues, reducing its capacity to 42 per cent.
- 2019 — Irrigators criticise the government for a lack of consultation and detail in the sudden decision to lower the wall.
- 2019 — Water releases start in October, as farmers furious about the lost water security step up their protests.
- 2019 — In November, a technical review outlining the issues with the dam’s original construction is released, prompting another independent review.
- 2019 — A preparedness report released in December finds the dam’s spillway is well below safety guidelines and would put lives at risk if it failed.
- 2020 — Amendments that pave the way for Sunwater to start pulling down the wall are rushed through parliament in February.
- 2020 — A Commission of Inquiry investigating the dam, presided over by former supreme court judge John Byrne, begins its hearings in Brisbane.
- 2020 — In March, the inquiry heads to Bundaberg where farmers ramp-up their campaign for the wall to be fixed, not lowered.
- 2020 — On April 30, the inquiry releases its report outlining the design failure in the initial construction, and preparation work to lower the wall begins soon after, despite opponents concerns about the economic cost.
- 2020 — Later that month, farmers take legal action in an attempt to stop the wall being lowered, which fails, and the work begins.
- 2020 — In July, 2,500 claimants join a class action against the Queensland government, claiming damages for losses associated with water insecurity.
- 2020 — Strength testing begins as the work to reduce the wall nears completion in September.
- 2021 — Work on lowering the wall resumes after the wet season ends, but the battle over water security rages on, with irrigators warned to prepare for insecure supply despite decent rain that saw the now lower storage overflow.
- 2021 — On Christmas Eve the Queensland government commits to returning the dam wall to its original height.
- 2022 — The state government announces the restoration of the wall will cost $1.2 billion, and calls for the federal government to fund half of the project.
- 2022 — Heading into a federal election campaign, LNP Member for Hinkler and Water Minister Keith Pitt commits $600 million to the project.
- 2022 — After the Coalition loses the election, farmers raise fears the restoration is taking too long, and call for the new Labor government to fund it.
- 2022 — Amid sweeping cuts to other water projects, the October budget confirms the federal government will provide $600 million for the dam wall’s restoration.
- 2023 — Early works to prepare for the wall’s restoration begin, ahead of major works due to start in 2024.
- 2024 — The Queensland government announces the wall will be completely rebuilt, after investigations reveal the existing wall cannot be repaired.